Buildings are coming down June 1

Monitor Staff

Hang on for a minute...we're trying to find some more stories you might like.


Email This Story






Ohlone is gearing up for a busy summer, as instruction and student services move to the Newark campus to make way for the demolition of Buildings 1, 2 and 8 and other construction projects on the Fremont campus.
Hard demolition will begin June 1 and continue through mid-August, with construction starting in the fall semester. Building 7 staff will move to Hyman Hall and Newark at the end of May and remain through early August.
The new five-story, 900-space parking structure on the south side of campus is nearing completion. Lot P will be closed from May 14 through mid-June, and close-out work will continue through July. A ribbon-cutting is scheduled for Aug. 12.
Other projects will include re-roofing of the Smith Center and the TV, radio and dance studios, installation of utility infrastructure, and tree pruning on Olive Lane.
AC Transit will stop bus service to the Fremont campus from May 25 through Aug. 23. Bus stops at the front of the campus on Mission Boulevard will continue to operate.

Leave a Comment

If you want a picture to show with your comment, go get a gravatar.




Hang on for a minute...we're trying to find some more stories you might like.


Email This Story






The student news site of Ohlone College
Buildings are coming down June 1